Noi Bai-Lao Cai expressway facing difficulties

Vietnam Expressway Corp (VEC) reported that the Noi Bai-Lao Cai expressway project was facing financial difficulties because of lack of 448 billion dong in corresponding capital.
Although 2 trillion dong of the project bonds were issued under the Ministry of Finance’s guarantee, but the project still is short of 448 billion dong.

Actualized work of the project in Jan-July (2011) reached 907 billion dong and the disbursed capital volume was nearly 840 billion dong, fulfilling 22.4% of the year’s plan. Since the beginning of the project, actualized workload has gained 4.133 trillion dong and 5.195 trillion dong has been disbursed, reaching 26% of total investment capital. – Vietbiz24

Tags:

Posted by VBN on Aug 19 2011. Filed under Transportation. You can follow any responses to this entry through the RSS 2.0. You can leave a response or trackback to this entry

You must be logged in to post a comment Login

Stay informed everyday

Subscribe to free RSS and email updates from Vietnam Business News

Subscribe via Email Subscribe in a Reader Follow us on Twitter Connect on Facebook

RSS China Business News

  • Copper up, but demand jitters cap gains
  • Gold prices fall 1 percent, silver was down 0.5 percent at $41.40 an ounce
  • Gold price in Hong Kong opens at 17,440 HK dollars per tael on Wednesday
  • Gold sheds 3 pc in choppiest day in two weeks
  • Appliance retailers eye shopping fest to boost sales
  • Stock break four-day losing streak
  • Swedish auto maker Saab files for bankruptcy protection
  • Chinese tourists to Sri Lanka almost double

Sponsored

Looking for an overseas forex broker?