Power supply projects begin Central Highlands operations

The National Power Transmission Corporation (NPT), under the Electricity of Viet Nam (EVN), early this week put into operation the 500-kV substation in the Central Highland province of Dak Nong and a 220-kV transmission line for the Dong Nai 3 Hydropower Plant— Dak Nong.

The projects were completed one month earlier than expected.

In order to transmit electricity from Dong Nai 3 and 4 hydropower plants which will start operation by the end of this year, the EVN has assigned NPT to invest in three projects of the national grid.

They are the 500-kV Dak Nong substation with a capacity of 900MVA, 30 kilometres of a 220-kV transmission line for Dong Nai 3 Hydropower Plant–Dak Noâng, and a 220-kV transmission line for Dong Nai 4 Hydropower Plant–Dak Noâng, with a total investment of VND720 billion (US$37 million).

The third project is expected to join the national grid soon.

A year ago, the NPT began operation of the 220 kV Tam Ky substation and 45 kilometres of a 220-kV transmission line for the Song Tranh 2 Hydropower Plant in Tam Ky Town in the central province of Quang Nam. — VNS

Tags: ,

Posted by VBN on Nov 18 2010. Filed under Energy. You can follow any responses to this entry through the RSS 2.0. You can leave a response or trackback to this entry

You must be logged in to post a comment Login

Stay informed everyday

Subscribe to free RSS and email updates from Vietnam Business News

Subscribe via Email Subscribe in a Reader Follow us on Twitter Connect on Facebook

RSS China Business News

  • Chinese tire exports decline after WTO ruling
  • China arrests 32 for producing, selling illegal cooking oil
  • Banks warned of risks in commercial property
  • Aug steel output dips, Baosteel ups Oct prices
  • Latin American agribusiness want Chinese investors
  • Kumho Tire sales plunge after quality scandal
  • Nissan gets OK to sell electric car Leaf in China
  • Better investment environment sought

Sponsored

Looking for an overseas forex broker?