Nam Cong 3 hydropower plant officially operates in Q4
Lilama Joint Stock Co No 10 (coded L10) announced that the company planned to put into operation the first turbine of Nam Cong 3 hydropower plant in Q4 and the second one by the end of this year.
Nam Cong 3 hydropower plant has two turbines with total designed capacity of 8MW. Lilama 10 was the main investor for this project with total investment capital of 227 billion dong. The hydropower plant was built under BOO method (Building- Operating- Owning).
The construction works started on November 28, 2007 and was expected to last for two years. One in operation, Nam Cong 3 hydropower plant would supply the national grid 35.46 million KWh.